Dick Steinkamp
Well-known member
I picked up what was described as "a good used motor" but with no history. I've taken it apart down to the long block to inspect it and fix any thing that needs fixing prior to putting it into service.
The babbitt was somewhat of a mystery to me. Under each rod and main bolt was a single .035 shim (yes, .035). The babbitt looked very good with little wear. The rods plastigauged at .003 and the mains at .002 with the single shims in place.
I plan to use some new shim packs and get the clearances closer to .001-.0015, but why the single .035 shims?
My THEORY is that in the babbitt pouring and finishing process, the rods and mains are assembled with the single shims, then line bored to the crank dimension plus the desired clearance. The motor is then assembled with the shims used in this process. Is this close?
The babbitt was somewhat of a mystery to me. Under each rod and main bolt was a single .035 shim (yes, .035). The babbitt looked very good with little wear. The rods plastigauged at .003 and the mains at .002 with the single shims in place.
I plan to use some new shim packs and get the clearances closer to .001-.0015, but why the single .035 shims?
My THEORY is that in the babbitt pouring and finishing process, the rods and mains are assembled with the single shims, then line bored to the crank dimension plus the desired clearance. The motor is then assembled with the shims used in this process. Is this close?